project creation in sap fico by satty
1.CREATION OF PROJECT TEMPLATE:
SPRO> GOTO> PROJECT MANAGEMENT
FROM THE MENU SELECT GOTO> PROJECT TEMPLATE
SELECT INSERT LINE BUTTON
21 OPEN
22 IN PROCESS
23 FINISHED
SAVE
SELECT THE ITEMS AND SELECT LEFT ARROW AND SAVE
2.CREATION OF PROJECT:
SPRO>GOTO> PROJECT MANAGEMENT
SELECT CREATE BUTTON
PROJECT NAME: DRL
ENTER
DESCRIPTION: DRL FI PROJECT
PERSON RESPONSIBLE: USERID OF FI CONSULTANT
PLAN DATA:
START DATE: 01.06.2010
END DATE: 30.06.2010
ACTUAL DATA:
START DATE: 01.06.2010
END DATE--BLANK
SAVE
SELECT SCOPE TAB
SELECT SPECIFY PROJECT SCOPE BY MAKING MANUAL SELECTION IN REFERENCE IMG RADIO BUTTON
SELECT SPECIFY SCOPE BUTTON
KEEP THE CURSOR ON ENTERPRISE STRUCTURE AND FINANCIAL ACCOUNTING
PRESS SELECT BUTTON
ENTER
SELECT GENERATE PROJECT IMG BUTTON
ENTER
ENTER ONCE AGAIN
SELECT PROJECT SCOPE BY CHOOSING APPLICATION COMPONENTS AND COUNTRIES RADIO BUTTON
SELECT GENRATE PROJECT IMG BUTTON
SELECT ENTER
SELECT ENTER ONCE AGAIN
SELECT PROJECT MEMBERS TAB
GIVE PROJECT MEMBERS USER ID
SAVE
SELECT BACK ARROW 2 TIMES
SELECT ADD TO WORKLISK BUTTON
SELECT DRL
ENTER
WE WILL GET ON SCREEN DRL PROJECT
DOUBLE CLICK ON DRL PROJECT
STATUS: 21
PLAN START DATE: 01.06.2010
PLAN END DATE: 01.06.2010
ACTUAL START DATE: 01.06.2010
END: BLANK
SELECT MEMO TAB: FI CONSULTANT WAS NOT WELL
SAVE
SELECT ENTERPRISE STRUCTURE> DEFINITION>FINANCIAL ACCOUNTING> DEFINE COMPANY
CREATE COMPANY: 123
SAVE
SELECT STATUS INFORMATION BUTTON
SELECT 23 FINISHED
SELECT GENERAL TAB
IT SHOWS
PLAN DATA:
START DATE: 01.06.2010
END DATE: 01.06.2010
ACTUALDATA:
START DATE: 01.06.2010
END DATE: 02.06.2010
SAVE
SELECT BACKARROW
SELECT DRL PROJECT
FROM THE MENU GOTO:< PROJECT ANALYSIS
PROJECT NAME: DRL
EXECUTE
WE KNOW THE STATUS OF EACH AND EVERY ACTIVITY
SPRO> GOTO> PROJECT MANAGEMENT
FROM THE MENU SELECT GOTO> PROJECT TEMPLATE
SELECT INSERT LINE BUTTON
21 OPEN
22 IN PROCESS
23 FINISHED
SAVE
SELECT THE ITEMS AND SELECT LEFT ARROW AND SAVE
2.CREATION OF PROJECT:
SPRO>GOTO> PROJECT MANAGEMENT
SELECT CREATE BUTTON
PROJECT NAME: DRL
ENTER
DESCRIPTION: DRL FI PROJECT
PERSON RESPONSIBLE: USERID OF FI CONSULTANT
PLAN DATA:
START DATE: 01.06.2010
END DATE: 30.06.2010
ACTUAL DATA:
START DATE: 01.06.2010
END DATE--BLANK
SAVE
SELECT SCOPE TAB
SELECT SPECIFY PROJECT SCOPE BY MAKING MANUAL SELECTION IN REFERENCE IMG RADIO BUTTON
SELECT SPECIFY SCOPE BUTTON
KEEP THE CURSOR ON ENTERPRISE STRUCTURE AND FINANCIAL ACCOUNTING
PRESS SELECT BUTTON
ENTER
SELECT GENERATE PROJECT IMG BUTTON
ENTER
ENTER ONCE AGAIN
SELECT PROJECT SCOPE BY CHOOSING APPLICATION COMPONENTS AND COUNTRIES RADIO BUTTON
SELECT GENRATE PROJECT IMG BUTTON
SELECT ENTER
SELECT ENTER ONCE AGAIN
SELECT PROJECT MEMBERS TAB
GIVE PROJECT MEMBERS USER ID
SAVE
SELECT BACK ARROW 2 TIMES
SELECT ADD TO WORKLISK BUTTON
SELECT DRL
ENTER
WE WILL GET ON SCREEN DRL PROJECT
DOUBLE CLICK ON DRL PROJECT
STATUS: 21
PLAN START DATE: 01.06.2010
PLAN END DATE: 01.06.2010
ACTUAL START DATE: 01.06.2010
END: BLANK
SELECT MEMO TAB: FI CONSULTANT WAS NOT WELL
SAVE
SELECT ENTERPRISE STRUCTURE> DEFINITION>FINANCIAL ACCOUNTING> DEFINE COMPANY
CREATE COMPANY: 123
SAVE
SELECT STATUS INFORMATION BUTTON
SELECT 23 FINISHED
SELECT GENERAL TAB
IT SHOWS
PLAN DATA:
START DATE: 01.06.2010
END DATE: 01.06.2010
ACTUALDATA:
START DATE: 01.06.2010
END DATE: 02.06.2010
SAVE
SELECT BACKARROW
SELECT DRL PROJECT
FROM THE MENU GOTO:< PROJECT ANALYSIS
PROJECT NAME: DRL
EXECUTE
WE KNOW THE STATUS OF EACH AND EVERY ACTIVITY